EasyManua.ls Logo

Giersch RG30 - Measuring Ionisation Current; Servicing Air Pressure Monitor

Giersch RG30
32 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
26
E.04.99 • G. 13.11.07
Service instructions/dimensions
Measuring ionisation current
The ionisation current must be measured during bur-
ner start-up and maintenance or after a fault indication
in the control box.
Measurement of ionisation current shortly after burner
start during:
Maintenance
Start-up
Fault indication.
The ionisation current can also be read out as a
percentage via SatroPen.
To do so:
Open plug connection between cable to control box and cable from ionisation electrode.
Connect ammeter in series. Measuring range 0...200 µA DC.
l > 2 µA - OK
l < 2 µA - Unsafe operation !
- Clean burner pipe
- Bend ionisation rod in flame area
- If necessary, replace combination electrode
- If necessary, reverse polarity on ignition transformer (induction current)
- Eliminate moisture and deposits.
Servicing air pressure monitor
Detach silicone connecting hose and clean, check
switching function.
Replace air pressure monitor if switching function is
no longer O.K.
To do so:
Switch burner voltage-free
and disconnect (7-pin connector X11).
Unscrew cover.
Disconnect electrical connectors.
Release retaining screws on motor.
Reassemble in reverse order.
“+” denotes the connecting point for
pressure metering connection !