GMV DC Inverter VRF 
35 
 
Fig.3.6.2 
2)  When the vacuum pump is turned off to stop vacuuming, the valve should be closed at 
first and then cut off the power for the vacuum pump.   
3)  Keep the vacuum for 2 hours and confirm that the pressure of the vacuum gauge has not 
risen. 
3.7 Additional Refrigerant Charging 
3.7.1 Calculation Method of Adding Refrigerant   
Total refrigerant charging amount R= Pipeline charging amount A + ∑charging amount B of every 
module. 
(1)  Pipeline charging amount: 
Pipeline charging amount A= ∑Liquid pipe length × refrigerant charging amount of every 1m liquid 
pipe. 
Diameter of 
liquid pipe   
Φ28.6  Φ25.4  Φ22.2  Φ19.05  Φ15.9  Φ12.7  Φ9.52  Φ6.35 
(2)  Σ Refrigerant charging amount B of every module 
Refrigerant charging amount B of every 
②
Module capacity(kW) 
IDU/ODU rated capacity 
collocation ratio C 
①
 
Quantity of 
indoor unit 
22.4  28  33.5  40  45  50.4  56  61.5  68 
50%≤C≤70% 
70%
<
C≤90% 
≥4  1  1  1  2  2  2.5  3  3.5  3.5 
90%
<
C≤105% 
105%
<