7
3. Delivery and handling
3.1 Delivery
The pumps are tested 100 % before leaving the factory. The test
includes a function test where the pump performance is
measured to ensure that the pump meets requirements of
relevant standards. Test certificates are available from Grundfos.
The pumps are delivered from the factory in a carton with a
wooden bottom designed for transport by equipment such as a
forklift truck.
Pump motors as from 4 kW are supplied with lifting eyes.
3.2 Handling
Pumps fitted with motors should be lifted by means of nylon
straps and shackles, if required. See fig. 1.
Fig. 1 Correct lifting of pump without base frame
Fig. 2 Correct lifting of pump with base frame
Fig. 3 Incorrect lifting of pump
The following is supplied:
Unit without motor
and pump
Unit without motor
Complete unit
Pump zz
Base frame zz
Electric motor, mounting designation
B 5 or B 35
z
Installation and operating instructions zz
Warning
Pump motors as from 4 kW are supplied with
lifting eyes which must not be used for lifting the
entire pump unit. See fig. 2.
TM03 3973 1306