4. Installation
36 PNEG-2381 2000 Series U-Trough Bin Sweep Auger Unload System (72' - 78')
3. Install the incline elbow assembly (84) on the end of the unloader. Insert the incline shaft (85) into
the flight bushing. Secure the incline elbow assembly (84) to the unloader end by installing the eight
nuts and bolts removed in Step 1 on Page 35 around the perimeter of the box flange (80). Install the
two 3-1/2" bolts and nuts in the flight bushing to couple the flighting. (See Figure 4AS.)
Figure 4AS
4. Prepare the powerhead (67) for installation: Move the hanger bushing bracket (86) up 1/2" by
removing the four bolts, securing the hanger bushing bracket (86) and re-installing them using the
lower set of holes (88). (See Figure 4AT and Figure 4AU.)
Figure 4AT Figure 4AU
85
80
80
80
80
Ref # Description
80 Box Flange Perimeter
85 Incline Shaft (Shown out of normal position)
86
67
86
88
87
Ref # Description Ref # Description
67 Powerhead 87 Upper Holes
86 Hanger Bushing Bracket
88 Lower Holes

Other manuals for GSi 2000 Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GSi 2000 Series and is the answer not in the manual?

GSi 2000 Series Specifications

General IconGeneral
BrandGSi
Model2000 Series
CategoryFarm Equipment
LanguageEnglish

Related product manuals