3.5.3  RCIM-4-way cassette (compact) (0.8-2.0)FSN2
  
Refrigerant pipe installation
The  correct  position  for  the  gas  refrigerant  pipe  connection  is 
shown  below.  The  pipe  connection  must  be  accessible  from  all 
directions (above, left or right).
 
Models (1) Gas pipe mm (inches) (2) Liquid pipe mm (inches)
RCIM-(0.8-1.5)FSN2E Ø12.70 (1/2)
Ø6.35 (1/4)
RCIM-2.0FSN2E Ø15.88 (5/8)
  
Drain pipe installation
The correct position for the drain hose connection is shown below.
Prepare a polyvinyl chloride (PVC) pipe with an outer diameter of 
32 mm.
Secure the pipe with the clamp and adhesive supplied.
Drain pipe connection
 
The drain hose must have a gradient of 1% (1/100) to 4% (1/25).