REMOVE THE RELAY MODULE FROM ITS 
SUB BASE AND FIX THE SUB BASE 
1.  Loosen the M3 fixing screw as shown in Fig. 1 by 
about eight turns using a Philips head screwdriver. 
2.  Take the subbase and cover with both hands and 
unfold them gently. Fold the relay module 
upwards, the turning point is on the top. Do not 
apply excessive force, otherwise damage may 
occur. 
3.  Punch out the needed conduit knockout holes for 
the wiring as shown in Figs 1 and 2, and install the 
wiring conduit(s). 
4.  Using the fixing screws, mount the subbase in the 
specified position. 
 Avoid to overtighten the fixation screw on the 
front of the device, to avoid damaging the 
(Phillips) head of the screw. 
 
WIRING THE RELAY MODULE BOTTOM 
TERMINALS 
1.  For applications with a UV detector, remove the 
jumper terminal located at the terminal block on 
the bottom of the relay module. 
2.  For applications using remote communication, 
connect communication cable to “BUS” terminal 
located at the terminal block on the bottom of the 
relay module. In addition, set the communication 
address uring the rotary switches at the bottom of 
the relay module. 
 
WIRING THE SUB BASE 
1.  Fig. 2 shows the layout of the terminals on the 
subbase, and Figs. 3-1 to 3-3 show examples of 
connections to external equipment. Regarding the 
wiring to the flame detector, refer to Fig. 4. 
2.  When using Intermittent Pilot, connect the pilot 
valve to Terminal 5. Connect the main valves to 
Terminal 7 (Enhanced and Ultimate models: 
connect main valve 1 to Terminal 7 and main valve 
2 to Terminal 12 for the VPS function) 
3.  When using Interrupted Pilot, connect the pilot 
valve to Terminal 6. Connect the main valves to 
Terminal 7 (Enhanced and Ultimate models: 
connect main valve 1 to Terminal 7 and main valve 
2 to Terminal 12 for the VPS function) 
4.  When using direct ignition (DBI), jumper Terminals 
15 and 22. And connect the Main(DBI) valves to 
Terminal 5.   
5.  When not using purge position interlock, jumper 
Terminals 15 and 16. 
6.  When not using start position interlock, jumper 
Terminals 13 and 17. 
7.  When not purge and start position interlocks, 
jumper Terminals 15 and 16 as well as Terminals 
13 and 17 simultaneously. 
8.  Connect the safety switch circuit (lockout 
interlocks) between Terminals 15 and 18. The 
safety switch circuit must be closed always, 
otherwise a lockout occurs immediately. 
9.  For non-floating mains power grids (Neutral to 
Ground), connect the Line-L to Terminal 1 and the 
Line-N to Terminal 2. Use a correct fuse: 10A fast 
blow maximum. 
10. Check all wiring circuits and assure that the 
correct fuse is installed. Check the correct voltage.   
11. Finally plug the relay module on to its sub base 
and fix it with the M3 fixing screw. Do not overtight 
the screw. 
12. When using a surge absorber, connect it between 
Terminal 2 and application ground. 
13. Connect the mains supply voltage using 0.75mm
2
 
or larger lead wire. 
14. Never connect blank stripped wires to the wiring 
sub base. Loose wire strands may cause short 
circuits to electrically safe contacts which may 
cause an electrical shock hazard. 
 
 Always use cable lugs to attach the wires to the 
sub base.   
See Fig 2-1 for do’s and don’ts about wiring. 
 
 
 
 
Fig. 2-1: Wiring the sub base terminals