UPS5000-E-(50 kVA-300 kVA)
User Manual (50 kVA Power Modules)
3 Installation
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
66
3.2.3.4 Connecting the BCB box
Open the cover on the BCB box, and connect the BCB ports on the dry contact card to the
control signal ports on the BCB box. For details, see the PDC-(0250, 0400, 0630)
DC0384BXA BCB Box User Manual or PDU8000-(0125, 0250, 0400, 0630, 0800)
DCV8-BXA001 BCB Box User Manual.
3.2.3.5 Connecting the BBB box
Connect the BBB box. For details, see the PDU8000-(0630, 1250, 2000) DCV8-BGA001 BBB
Box User Manual.
3.2.3.6 Installing a Battery Grounding Failure Detector
Procedure
Step 1 Install a battery grounding failure detector. For the installation method, see UPS5000 Battery
Grounding Failure Detector User Manual.
Figure 3-23 shows the position for a battery grounding failure detector in a
UPS5000E-200K-SM.
Figure 3-24 shows the position for a battery grounding failure detector in a
UPS5000E-200K-FM.
Figure 3-25 shows the position for a battery grounding failure detector in a
UPS5000E-300K-SM.
Figure 3-26 shows the position for a battery grounding failure detector in a
UPS5000E-300K-SMT.
Figure 3-23 Position of a battery grounding failure detector in a UPS5000E-200K-SM
(1) Battery grounding failure detector

Table of Contents

Other manuals for Huawei UPS5000-E-200K-FM

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei UPS5000-E-200K-FM and is the answer not in the manual?

Huawei UPS5000-E-200K-FM Specifications

General IconGeneral
BrandHuawei
ModelUPS5000-E-200K-FM
CategoryControl Unit
LanguageEnglish

Related product manuals