Checking piping connections Check
Check to see that adequate gas pressure is present at the inlet gas supply test port.
Connect a manometer and open the gas control valve. Requirements are minimum 4" w.c
and maximum 14" w.c.
Check that there are no gas leaks.
All connections are pressure tested and leak free.
All piping flushed to ensure all air is removed.
Check valve is installed and the external pump is flowing in the correct direction.
Checking venting connections Check
All connections are pressure tested and leak free.
All vent pipe is sized correctly and joints are sealed.
Powering on the boiler Check
Perform a final check of electrical wiring, and provide power to the boiler to initialize
operation.
64
Section: Before operating the boiler

Table of Contents

Other manuals for IBC SL 26-260 G3

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the IBC SL 26-260 G3 and is the answer not in the manual?

IBC SL 26-260 G3 Specifications

General IconGeneral
BrandIBC
ModelSL 26-260 G3
CategoryBoiler
LanguageEnglish

Related product manuals