Page #10 background imageLoading...
Page #10 background image
FanCoils
INSTALLATION,OPERATION,&MAINTENANCEMANUAL
10
SECTIONTWO
—StartUp,Cont'd.
Eachunitshouldbecheckedfor:
1. freeblowerwheeloperation
2. loosewires
3. looseormissingaccesspanelsordoors
4. cleanlterofthepropersizeandtype
Exceptasrequiredduringstart-upandbalancingoperations,
nofancoilunitsshouldbeoperatedwithoutalltheproper
ductworkattached,supplyandreturngrillesinplace,andall
accessdoorsandpanelsinplaceandsecure.Failuretodo
socouldresultindamagetotheequipmentorbuildingand
furnishings,and/orvoidallmanufacturerswarranties.
Cooling/Heating System
Priortothewatersystemstart-upandbalancing,the
chilled/hotwatersystemsshouldbeushedtocleanout
dirtanddebriswhichmayhavecollectedinthepiping
duringconstruction.Duringthisprocedure,allunitservice
valvesmustbeintheclosedposition.Thisprevents
foreignmatterfromenteringtheunitandcloggingthe
valvesandmeteringdevices.Strainersshouldbeinstalled
inthepipingmainstopreventthismaterialfromentering
theunitsduringnormaloperation.
Duringsystemlling,airventingfromtheunitis
accomplishedbytheuseofthestandard,manualairvent
tting,ortheoptional,automaticairventttinginstalled
onthecoil.ManualairventsarebasicallySchradervalves.
Toventtheairfromthecoil,depressthevalveuntiltheair
hasventedthecoil.Whenwaterbeginstoescapethrough
thevalve,releasethevalve.Automaticairventsmaybe
unscrewedoneturncounterclockwisetospeedinitial
venting,butshouldbescrewedinforautomaticventing
afterstart-upoperations.
CAUTION! The air vent provided on the unit is
not intended to replace the main system air vents
and may not release air trapped in other parts of the
system. Inspect the entire system for potential air traps
and vent those areas as required, independently. In
addition, some systems may require repeated venting over
a period of time to properly eliminate air from the system.
Air System Balancing
Allductworkmustbecompleteandconnected.Allgrilles,
lters,andaccessdoorsandpanelsmustbeproperly
installedtoestablishactualsystemoperatingconditions
BEFOREbeginningairbalancingoperations.
Eachindividualunitandtheattachedductworkisa
uniquesystemwithitsownoperatingcharacteristics.For
thisreason,airbalancingisnormallydonebybalance
specialistswhoarefamiliarwithallproceduresrequired
toproperlyestablishairdistributionandfan-system
operatingconditions.Theseproceduresshouldnotbe
attemptedbyunqualiedpersonnel.
Exposedunitswithoutductworkdonotrequireair
balancingotherthanselectingthedesiredfanspeed.
Afterpropersystemoperationisestablished,theactual
unitairdeliveryandtheactualfanmotoramperagedraw
foreachunitshouldberecordedinaconvenientplacefor
futurereference.
Eco-telligent
®
Motor
IftheunitisequippedwithanECMblower,additional
stepsmayberequiredduringtheairbalancingprocess.
Reviewprojectsubmittalsororderacknowledgment
todeterminewhichECMcontrolschemetheunithas.
Alternatively,matchthecontrolboardtotheillustrations.
CAUTION! Both of the procedures described
below require the control box to be powered
while adjustments are made. Line voltage components
are concealed behind a secondary cover. However,
installer should still take all reasonable precautions.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the IEC CPY 03 and is the answer not in the manual?

IEC CPY 03 Specifications

General IconGeneral
BrandIEC
ModelCPY 03
CategoryAir Conditioner
LanguageEnglish

Related product manuals