SET-UP PROCEDURES
Receiving and Handling
The machine is shipped to the customer in a box and fixed to a pallet.
Remove the strapping and the staples at the bottom of the box.
Lift off the box cover and sleeve.
Remove the mounting bolts and nuts, which secure the USA 20-SB to the shipping
pallet.
Lift the machine off the pallet and install it on your packaging line.
Remove all tie wraps and other shipping materials.
Note: After unpacking the machine, look for any damage that may have
occurred during shipping. Should the machine be damaged, file a claim
with the transport company and notify your Intertape representative.
Setting-up
1) General
The Carton Sealer must be installed on a near level ground.
Ensure that the machine is level and firmly on the ground (no rocking). Adjust the
rollers' height with the four (4) telescopic adjustment legs to accommodate conveyor
heights from 24 to 30 inches.
To adjust the Carton Sealer height,
jack up the machine to give ample
room to extend the legs. Using a
9/16" box end wrench, loosen the
eight (8) 1/2" hex head bolts. Adjust
the legs to the desired conveyor
height and tighten the bolts. Etched
scales on the legs facilitate
proportionate leveling.
Figure 4