UM062TW / UM562TW UDM10010-01
17
OPERATING INSTRUCTIONS
Once the HSD
2000-ETII Tape Heads (both bottom and top) have been loaded with tape
and threaded, the machine is ready to process regular slotted cartons. The following
instructions are presented in the order recommended for processing cartons successfully
through the USA 20-SB Carton Sealing machine.
1. Turn the Width Adjustment Handle to open the drive base in order to allow an empty
test carton to slide on the machine
2. Place an empty test carton with the flaps held in closed position onto the conveyor
rollers.
3. Adjust the self-centering drive belts by turning the Width Adjustment Handle.
4. Remove the test carton from the machine.
5. Ensure that the electrical power is on.
6. Switch the machine "on" with the start push button.
7. Process the first carton with the flaps in the closed position.
8. When the carton exits the Carton Sealer, process the next carton.
W
ARNING! ENSURE THAT THE OPERATOR'S HANDS ARE AWAY FROM THE MOVING BELTS
OF THE SIDE DRIVE BASE ASSEMBLY
.
Note: Should any problem occur during processing that requires halting the
machine, press the red "E-Stop" mushroom button.
Note: The machine should never be washed down or subjected to conditions
causing condensation on components.