5-76 BA 35203_04 * 3.0 * 35203_04_05_Bedienung.fm
5 Operation
Preparing machine travel on public roads
(wheel loader 352-04 S/L)
1. Empty the bucket, lower it to the ground and remove it from the
quickhitch facility
– see “Lower the attachment” on page 5-62,
– see “Unlocking an attachment” on page 5-41.
2. Install transport hooks E on the inside of the bucket.
3. Pick up and safely lock the bucket on transport hooks E
– see “Pick up the attachment” on page 5-58,
– see “Locking the attachment” on page 5-41.
4. Ensure that the bucket is visibly locked on either side with lock pins H.
Risk of damage to property due to squeezing or jamming the bucket
against the front wheels.
5. Align the bucket base parallel to the ground, remove the bucket teeth if
necessary.
6. Raise the loader unit to transport position.
➥ Ground clearance C about 250 mm (9.84 in).
7. Secure the joystick – see “Securing the control lever (joystick)/
switching off the operating hydraulics” on page 4-54.