LAUNCH Electronic Two-post Userโ
14
5๏ผ
๏ผ๏ผ
๏ผSolutions to FAQ
Symptom Reason Solution
Motor not operation
๎ Check the circuit breaker or fuse
๎ Check the voltage to the motor
๎ Limit switch is failed
โฆ Motor wire is burnt
๎ Replace the burnt fuse or reset the
circuit breaker
๎ Supply correct voltage for motor
๎ Replace the limit switch
โฆ Replace the motor
Motor is running, but
the lift canโt be raised.
๎ Motor rotation reversed
๎ Solenoid valve body open.
๎ Hydraulic pump sucks the air
๎ Suction tube is separate from the
hydraulic pump
๎ Low oil level
๎ Change the motor rotating direction by
changing wire connection.
๎ Repair or replace the solenoid valve
body
๎ Fasten all the suction pipe fittings
๎ Replace the suction tube
๎ Add the oil into the oil tank
Motor is running, the
lift can be raised
without load, but the
vehicle canโt be raised
๎ Motor is running under low voltage
๎ Impurities inside the solenoid valve
body
๎ Regulation pressure of safety valve is
incorrect
๎ Lift is overloaded
๎ Supply correct voltage to the motor
๎ Remove impurities from the solenoid
valve body.
๎ Adjust the safety valve
๎ Check the weight of the vehicle
The lift is lowering
slowly without
pressing the down
button
๎ Impurities on the solenoid valve body.
๎ External oil leakage
๎ Clean the solenoid valve body
๎ Repair the external leakage
The lifting speed is
slow or oil flows out of
the oil fill cap
๎ Air and oil are mixed
๎ Air and oil suction are mixed
๎ Oil return pipe is loosened
๎ Replace the hydraulic oil
๎ Fasten all the suction pipe fittings
๎ Re-install the oil return pipe
The lift canโt rise
horizontally
๎ Balance cable is not adjusted properly
๎ The lift is installed on the slop floor
๎ Adjust the balance cable to the proper
tension
๎ Shimming the columns to level the
lift(no more than 5mm), If exceeding
5mm, pour new concrete floor and
make it leveled. Refer to installation
description.
Anchor Bolt is not
fastened
๎ Hole is drilled too big
๎ Concrete floor thickness or fastening
force is insufficient
๎ Pour the fast curing concrete into the
big hole and reinstall the anchor Bolt ,
or use new drill to drill the hole for
re-positioning the lift
๎ Cut open the old concrete and make
new concrete slab for the lift. Refer to
installation description.
(C) Diagtools; www.diagtools.eu; diagtools@diagtools.lv; Pernavas 43A, Riga, Latvia, LV-1009; +37129416069