First install extension column with column, then
use lifting equipment to place power side column upper
right to the location. Align the base plate of column with
the chalk line layout. Guided by holes on the base
plate of the column, use 5 concrete anchor bolts to fix it
onto the ground. Drill and install anchor Bolt s at one
time, during the drilling process, ensure no movement
of the column.(Fig.8c) .
Fig.8c
Note
:
::
:
♦ Use sharp
Φ
ΦΦ
Φ
19mm concrete drill-bit to drill the
holes so as not to drill the hole too large,. Use
proper pneumatic tool to remove the dust from
the hole. The depth of the hole is the same as that
of the anchor Bolt . Insert the anchor Bolt and
make the washers lean against the base of the
column.
♦ Only use torque wrench instead of impact tools to
fasten anchor Bolt s. Insert proper steel shim
under the base seat of column to plumb the
column.
Note: The thickness of shims shouldn’t exceed
5mm.