21
Dismantling is performed in the reverse order to assembly
(see page 16).
When dismantling, do not remove the bracing elements such as
diagonal braces, guardrails or access decks until the basic towers
above them have been dismantled.
To lift out the individual parts, open the snap-on claws by pressing
their locking clips.
During assembly and dismantling, system decks or scaffolding
planks to DIN 4420-3 (minimum dimensions 28 x 4.5 x 220 cm)
must be installed as auxiliary decks at maximum height intervals
of 2.0 m. These auxiliary decks provide a safe footing for assembly
and dismantling, and must be removed again after assembly. Each
platform must be completely boarded.
The red locking clips of the decks permit effortless installation and
removal by a single person; first open them and place the deck with
the opened clips on the rung, then open the opposite clips and lift out
the deck.
8. DISMANTLING SEQUENCE according to
DIN EN 1004

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Layher ZIFA and is the answer not in the manual?

Layher ZIFA Specifications

General IconGeneral
BrandLayher
ModelZIFA
CategoryDesktop
LanguageEnglish