Loading tubing for YZ15/YZ25/YT15/YT25 pump head
1. Be sure the pump drive is turn off.
2. Pull the pull rod to the horizontal position, left the sliding block.
Loading the suitable tube.
YT15, YT25 pump heads only in the first installation tube need to a fine tuning
knob adjustment. First put the pressure tube clearance knob to the loose state
by counterclockwise.YZ15, YZ25 pump heads pressure tube clearance is
cannot adjust.
Throw up on one side of the tubing clamp, put tubing in, then pull another side
tubing clamp, put the tubing into the other side.
Tension with both hands on both ends of the tube, make it natural stretch, no
distortion, no deviation.