Applications Using A Single-Stage Thermostat
See Figure 68 for ignition control sequence
B - Heating Sequence -- Integrated Control Thermostat
Selection DIP Switch 1 ON in “Single-Stage” Position
NOTE - In these applications, two-stage heat will be initi-
ated by the integrated control if heating demand has not
been satised after the eld adjustable period (7 or 12
minutes).
1 -        
close sending a signal to the integrated control. The
integrated control runs a self-diagnostic program
and checks high temperature limit switches for
normally closed contacts and pressure switches for
normally open contacts. The combustion air inducer
is energized at low speed.
2 - Once the control receives a signal that the low
pressure switch has closed, the combustion air
inducer begins a 15-second pre-purge in low speed.
NOTE - If the low re pressure switch does not close
the combustion air inducer will switch to high re.
After a 15 second pre-purge the high re pressure
switch will close and the unit will begin operation on
high re. After 10 to 20 seconds of high re opera-
tion the unit will switch to low re.
3 - After the pre-purge is complete, a 20-second initial
ignitor warm-up period begins. The combustion air
inducer continues to operate at low speed.
4 - After the 20-second warm-up period has ended,
 
and ignition occurs. At the same time, the control
module sends a signal to begin an indoor blower
30-second ON-delay. When the delay ends, the
        
heating speed and the HUM contacts are energized.
The integrated control also initiates a second-stage
on delay (factory-set at 7 minutes; adjustable to 12
minutes).
5 - If the heating demand continues beyond the
secondstage on delay, the integrated control
energizes the combustion air inducer at high speed.

pressure switch to make sure it is closed. The high

indoor blower motor is energized for operation at

6 -  
the combustion air inducer begins a 5-second low

󰀨

7 - When the combustion air post-purge period is
complete, the inducer and the HUM contacts are
de-energized. The indoor blower is de-energized at
 󰀨  
terminals.
1 stg heat demand
2 stg heat demand
15
ON
OFF
low speed CAI
35
1
Pre-Purge
Ignitor Warm-up
30* second
blower
“on” delay
Post
Purge
5 SEC80
ignitor
HEATING OPERATION WITH TWO-STAGE THERMOSTAT
low fire gas valve
indoor blower low heat
high speed CAI
high fire gas valve
indoor blower high heat
39
Trial For
Ignition
blower
“off”
delay
RECOGNITION PERIOD
30 seconds
* Conventional thermostat 30 seconds, communicating thermostat set for 30 adjustable 15 to 45 seconds.
Figure 67
heat demand
15
ON
OFF
low speed CAI
35
1
Pre-Purge
Ignitor Warm-up
30* second
blower
“on” delay
Post
Purge
5 SEC
80
ignitor
HEATING OPERATION WITH SINGLE STAGE THERMOSTAT
low fire gas valve
high speed CAI
high fire gas valve
indoor blower high heat
39
Trial For
Ignition
7 or 12 minutes after heating demand begins, furnace switches to high fire (depends on setting)
blowe
r
“off”
delay
indoor blower low heat
* Conventional thermostat 30 seconds, communicating thermostat set for 30 adjustable 15 to 45 seconds.