7 Commissioning
Commissioning steps
EDK82ZAFSC−100 DE/EN/FR 4.0
44
H2_Inbetriebnahmeschritte−−−−(DUMMYSEITEVOR)−−−
Commissioning steps
Step Procedure Description
1. Switch on the mains
voltage.
The basic device will be ready for operation after approx.
1 second.
The controller inhibit is active.
Drive response:
The green LED is blinking.
Keypad:
 (if attached)
2. Control digital inputs. Lenze setting:
l CW rotation:
E1, E2, E3, E4: LOW
l CCW rotation:
E1, E2, E3: LOW
E4: HIGH
Individual setting:
l Adapt digital inputs under C0007 or C0410.
l The digital inputs must be controlled so that the drive
can start via terminal after controller enable.
3. Provide a setpoint Lenze setting:
Setpoint: 0 ... +10 V
Individual setting:
l Depending on the position of the DIP switch at the
function module
apply master current to X3/8 or
Apply master voltage at X3/8.
l Check C0034.
4. Release the controller via
the terminal.
Lenze setting:
X3/28 = HIGH (+12 ... +30 V)
Drive response:
l The green LED is on.
l Keypad: goes off.
5. The drive should be running now.