INSTALLATION
21
ENGLISH
Main cause of gas leakage is defect in flaring work. Carry out correct flaring work in the following
procedure.
Cut the pipes and the cable
- Use the accessory piping kit or the pipes pur-
chased locally.
- Measure the distance between the indoor
and the outdoor unit.
- Cut the pipes a little more than measured
distance.
- Cut the cable 1.5 m more than the pipe
length.
Burrs removal
- Completely remove all burrs from the cut
cross section of pipe/tube.
- Put the end of the copper tube/pipe to down-
ward direction as you remove burrs in order
to avoid to let burrs drop in the tubing.
Flaring work
- Carry out flaring work using flaring tool as
shown below.
Firmly hold copper tube in a bar(or die) as in-
dicated dimension in the table above.
Check
- Compare the flared work with figure below.
- If flare is noted to be defective, cut off the
flared section and do flaring work again.
Indoor unit
[kW(Btu/h]
Pipe " A "
Gas Liquid Gas Liquid
< 5.6(19,100)
1/2" 1/4" 0.5~0.8 0~0.5
< 16.0(54,600)
5/8" 3/8" 0.8~1.0 0.5~0.8
< 22.4(76,400)
3/4" 3/8" 1.0~1.3 0.5~0.8