Please read the following check points and caution carefully as they imply the
critical contents which should be confirmed before performing the unpacking,
inspection, or installation, etc.
Check points upon receiving
1. A visual inspection inside and out should be performed immediately upon receipt of the ACB
and before removing it from the truck. If any damage or shortages are evident, a claim should be
filed at once with the carrier to the nearest LSIS sales office.
2. Unpacking them attentively to avoid dropping the products from carrying components and pallets.
3. Install the products to the final installation place after unpacking as soon as possible. If you cannot
install the products immediately, you had better not unpacking them. Keep the products indoor
around 15 and under 50% of humidity. Standard packing condition for domestic portage is not
suited to outdoor storage. If you cannot keep the maintenance above, you should inspect a degree
of the damages before you install the products. Unsuitable keeping does not guarantee good
qualities of the products and could occur additional danger of an accident.
Caution for installation inspection
1. Confirm all power sources are completely de-energized first.
2. Disconnect all electrical switches which may operate during inspection.
3. Disconnect all plugs connected to operating part of product (Shunt coil, OCR, etc.)
4. In case of Draw-out type, pull out the product until guideline comes to TESTED position
from cradle. (Basic inspection is available under TEST position.)
5. In case of detailed inspection, remove the product form cradle securely and put it to the
even stand.
6. Inspect product.
3. Check point and caution
E. Unpacking