4 Commissioning
4.1 Choice of commissioning  .......................................4-2
4.2 Serial commissioning  .............................................4-2
4.2.1 Serial commissioning with  D
RIVEMANAGER ............4-2
4.2.2 Serial commissioning with  K
EYPAD ......................4-4
4.3 Initial commissioning  .............................................4-6
4.3.1 Selecting the unit for speed values .......................4-8
4.3.2 Selecting preset solution ......................................4-9
4.3.3 Setting the motor and encoder ...........................4-11
4.3.4 Making basic settings  ........................................4-13
4.3.5 Setting function parameters ...............................4-14
4.3.6 Safety functions  .................................................4-15
4.3.7 Motor filter .........................................................4-16
4.3.8 Switching frequency  ..........................................4-16
4.3.9 Saving settings  ..................................................4-17
4.4 Test run  .................................................................4-18
4.5 Operation with  D
RIVEMANAGER ..............................4-22
4.6 Operation with K
EYPAD KP200 ...............................4-24
Attention: Commissioning must only be carried out by qualified 
electricians who have undergone instruction in the necessary 
accident prevention measures.