50 ALR 110F – 150F Product Manual ALR2-3
PART 3 - EXECUTION
3.01 INSTALLATION
A. Install in strict accordance with manufacturer’s requirements, shop drawings, and
contract documents.
B. Adjust and level chiller in alignment on supports.
C. Coordinate electrical installation with electrical contractor.
D. Coordinate controls with control contractor.
E. Provide all appurtenances required to insure a fully operational and functional
chiller.
3.02 START-UP
A. Ensure proper charge of refrigerant and oil.
B. Provide testing, and starting of machine, and instruct the Owner in its proper
operation and maintenance.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the McQuay ALR 110F and is the answer not in the manual?

McQuay ALR 110F Specifications

General IconGeneral
BrandMcQuay
ModelALR 110F
CategoryChiller
LanguageEnglish

Related product manuals