METTLER TOLEDO IND360fill/dose Application EtherNet/IP Engineering Notes
Set the maximum amount of time for the Fill or
Dose cycle to complete
[0 – 99999s]
The filling/dosing cycle has been started.
The cycle has been completed
Dump sequence is running.
Refill sequence is running.
Current speed is fast feed.
Spill sequence is running.
Upper refill limit reached.
Lower refill limit reached.
Unable to start due to incorrect starting weight
(e.g. start weight above target).
Initial feed timeout: weight value is not
changing for predefined time after process is
started.
Dump timeout exceeded. The Dump Timeout
determines the maximum acceptable amount of
time for the dump to complete.
Auto tare failed due to container out of tare
range.
Fault happened during filling.
Fault happened during dosing
Maximum allowed time (configurable) for
fill/dose cycle exceeded.
Refill timeout exceeded. The Refill Timeout
determines the maximum acceptable amount of
time for the refill to complete.
The final weight is over the predefined positive
tolerance.
The final weight is below the predefined
negative tolerance.
There is a maximum number of jog cycles for
automatic jog, this alert is raised when the
maximum number has been exceeded to
protect the equipment.
The amount of material filled or dispensed in
the last cycle.