10.4 Commissioning Trial Runs 
10.4.1 Commissioning test run of single refrigerant system 
Once all the pre-commissioning checks in Part 3, 10.3 “Pre-commissioning Checks” have been completed, a test run should 
be performed as described below and a V6-i Series System Commissioning Report (see Part 3, 11 “Appendix to Part 3 – 
System  Commissioning  Report”)  should  be  completed  as  a  record  of  the  operating  status  of  the  system  during 
commissioning. 
 
Note: When running the system for commissioning test runs, if the combination ratio is 100% or less, run all the indoor units 
and if the combination ratio is more than 100%, run indoor units with total capacity equal to the capacity of the outdoor 
unit. 
 
The test run procedure is as follows: 
1.  Open the outdoor unit liquid and gas stop valves. 
2.  Turn on the power to the outdoor unit.   
3.  If manual addressing is being used, set the addresses of each indoor unit. 
4.  Leave the power on for a minimum of 12 hours prior to running the system to ensure that the crankcase heaters have 
heated the compressor oil sufficiently. 
5.  Run the system: 
a)  Run the system in cooling mode with the following settings: temperature 17°C ; fan speed high.   
b)  After one hour, complete Sheet A of the system commissioning report then check the system parameters using 
the UP/DOWN button on the outdoor unit’s main PCB and complete the cooling mode columns of one Sheet D 
and one Sheet E of the system commissioning report for the outdoor unit. 
c)  Run the system in heating mode with the following settings: temperature 30°C ; fan speed high.   
d)  After one hour, complete Sheet B of the system commissioning report then check the system parameters using 
the UP/DOWN button on the outdoor unit’s main PCB and complete the heating mode columns of one Sheet D 
and one Sheet E of the system commissioning report for the outdoor unit. 
6.  Finally, complete Sheet C of the system commissioning report. 
 
10.4.2 Commissioning test run of multiple refrigerant systems 
Once  the  commissioning  test  run  of  each  refrigerant  system  has  been  satisfactorily  completed  as  per  Part  3,  10.4.1 
“Commissioning test run of single refrigerant system”, run the multiple systems that make up a project simultaneously and 
check for any abnormalities.