Chapter 4 - Installation
Startup checklist
The enclosed startup checklist guides the process of the machine installation and
checkout. The startup checklist forms must be completed and sent to Milltronics Mfg. to
activate the machine warranty. Use the startup checklist in conjunction with the
following outline when installing and setting up the machine.
Required Assembly
In some cases, parts of the machine are removed or adjusted for shipping purposes.
Qualified personnel (See the safety checklist on page 2 for qualifications) should install
and adjust as necessary according to the photos and descriptions.
Locate the leveling pads, and then thread them into
the machine base before setting the machine on
the floor.
Loosen and remove the mounting hardware for the
shipping bracket. Remove the bracket if it slides
out easily. It the bracket does not slide easily, wait
until the machine has been “homed”, or Z-axis
moved up for the first time, and then remove the
bracket.
If the swivel pendant box (if equipped) was
removed for shipping, install it as shown per the
instructions included.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Milltronics VM Series and is the answer not in the manual?

Milltronics VM Series Specifications

General IconGeneral
BrandMilltronics
ModelVM Series
CategoryIndustrial Equipment
LanguageEnglish

Related product manuals