3 System Description
3.1 Operating Procedures
The typical operating procedure of BA-88A is shown as follows:
Figure 3-1 Operating procedure
Lamp
stabilization
Reaction
All the
tests
finished
Temperature
stabilization
Other
tests
Procedures:
1 Empty the waste. Connect the waste tubing to the waste container. Prepare
the samples, reagents and distilled water;
2 Connect power cable correctly. Power on the analyzer. The instrument will
under go the initialization processes, including; system startup, hardware
self-check, parameters download, dark current testing. After initialization,
wait until the temperature and the light source are stable. The whole
process lasts for about 15 minutes;
3 After the system is stable, set the parameters of the tests, such as
wavelength, temperature, methods and etc. Start the test.