Chapter 4: Test the MyDro After Installation
and Commissioning
1. Check input voltages with a multi-meter.
2. Exercise all inputs and conrm that the LCD and web portal are displaying
the values correctly. Page relays and analog output (if in use) from the web
portal and conrm proper operation. As a reminder, the N/O and N/C termi-
nals on the output relays are opposite that of the Legacy RTU.
3. Conrm all automated remote control functions are working properly.
4. Conrm all fail-safe operations are working as desired. One way to do this is
to disconnect the antenna so that the RTU goes ofine.
5. Contact Mission Technical Support so that we can associate the new radio
identier (IMEI) with the data from the previous RTU.