If your installation is equipped with water treatment devices (chlorine, brome feeder, salt water
chlorine generator, others) the by-pass must be installed before the water treatment devices,
with a non-return check valve between the by-pass and water treatment devices.
Water inlet and outlet are designed to be connected to rigid pressure PVC tube (for swimming
pool) Ø50 mm, directly glued to the half union connectors provided.
Inlet water tube must be connected to connection labelled:
Outlet water tube must be connected to connection labelled:
Water tubes must be fixed on the floor or the walls, so the heat pump will not support the
weight of the water inside the plumbing.