5 START-UP
PAGE
5.0R
text no.
R 05005-1/2
issued: 14.11.2016 Revision: 3
copy to:
■ Before the initial start-up, fill the pump with the
conveyor medium or another compatible medium.
■ If necessary, fill the pump externally.
■ Switch the pump on and check the direction of
rotation.
If the direction of rotation corresponds to the
specification on the name plate, this also means the
required direction of delivery is provided.
IPP - EN - EN_05005_20161114/2 - D8411276 - 4300003998 - 000100 - NPS - 00229929 N 2018-02-21 19:03:25