101
TRX Series II - Installation - Startup - Maintenance Instructions
Table 44 - Installation Checklist
Wiring Yes Note
Has the power and control been wired per boiler wiring diagram, this manual?
Is the main electrical connection polarity within boiler requirements?
Does the power supply voltage agree with the boiler rating plate? 120V AC?
Start-Up, Adjust, and Test Yes Note
Has the boiler been started?
If necessary, has the boiler gas valve been adjusted?
Has the installation been customized per installation location requirements?
Have all customized system parameters been tested?
Has proper boiler operation been confirmed?
Burner Flame Yes Note
Has the burner flame been checked?
Have combustion values been verified with a calibrated combustion analyzer?
If the flame does not appear normal, it may need to be cleaned by a qualified service technician. See flame
sight glass window location.
Final Installation Approvals
Signed by Technician Date
Part 12 - Installation Checklist