CompoWay/F
SECTION 2 CompoWay/F Communications Procedures
2-20
(3) Operation Commands and Precautions
Communications Writing
Set the Communications Writing parameter to “ON: enabled” or “OFF:
disabled” with the related information setting. The setting can be
accepted in both setup area 0 and setup area 1. An operation error will
occur, however, if enabling or disabling communications writing is set
for an event input.
RUN/STOP
Set control to “run” or “stop” with the related information setting. The
setting can be accepted in both setup area 0 and setup area 1. An
operation error will occur, however, if RUN/STOP is set for an event
input.
Bank Change
Select a bank from 0 to 7 with the related information setting. The
setting can be accepted in both setup area 0 and setup area 1. An
operation error will occur in the following situations.
When AT is being executed
When a bank change is set for the event input (Bank Numbers Used
parameter setting > 0)
When the program pattern is set to any setting other than OFF, the
bank number must be between 00 and the bank set for the Valid
Program Bank, and a parameter error will occur if the related infor-
mation setting exceeds the bank set for the Valid Program Bank
parameter setting.
AT Execute/Cancel
Set AT (auto-tuning) to “execute” or “cancel” with the related information
setting. This command can be accepted in setup area 0 only. An
“operation error” will be generated in the following instances:
When the RUN/STOP parameter is set to “stop”
When the command is executed in “setup area 1
When ON/OFF control is being used
When 40% AT is specified during 100% AT execution.
When 100% AT is specified during 40% AT execution.
In addition, a parameter error will occur if 40% AT is specified during
heating and cooling control or during position-proportional floating
control.
Note: If the same type of AT execution is specified during AT execution
(e.g., if 100% AT is specified during 100% AT execution), the AT
will not be restarted and the operation will end in normal
completion with no processing.

Table of Contents

Other manuals for Omron E5CN-H

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Omron E5CN-H and is the answer not in the manual?

Omron E5CN-H Specifications

General IconGeneral
BrandOmron
ModelE5CN-H
CategoryController
LanguageEnglish

Related product manuals