59
Parker Hannin Corporation
Hydraulic Pump/Motor Division
Greeneville, Tennessee USA
HY13-1524-002-M1/US
Assembly
Service Manual
HTG Series Integrated Hydrostatic Transmission
HY13-1528-001-M1/US—HTG Series Service Manual
Reassembly
Step
InstructionIllustration
Torque nut 1. Using a strap wrench or similar, hold
pulling while torquing nut.
2. Torque nut to 55-70 ft-lbs.
Fill with HT-1000™ oil.
Replace vent plug.
Install Woodruff Key.
Install brake assembly.
1. Hand start hollow hex plug.
2. Tighten with a 5/16” hex wrench
3. Torque to 100-120 in-lbs.
Fill transmission to the expansion tank tting
with approximately three (3) quarts of
HT-1000™ oil.
May need to use brass hammer to seat the
Woodruff Key into shaft.
Place assembly over shaft, aligning with four
bolt holes on motor housing.
Install four brake assembly
bolts.
1. Tighten by hand