8
Translation of the Original Instructions for Use
Platform Connection CB 160
Introduction
4. Inspections
4.1 Safety check
The contractor arranges for an inspec-
tion to take place before initial opera-
tions of the load-carrying equipment be-
gin which is to be carried out by a
suitably qualified person.
4.2 Implementing the inspection
The inspection includes a visual and
functional check.
Deformation and elongation of the
components.
Wear in excess of 10%.
– Mechanical damage.
Availability of all components.
Damage due to corrosion.
Cracks, pressure points, indentations
on weld seams and components.
Only PERI original components are to
be used.
Signs of non-permissible heat treat-
ment or exposure to fire.
4.3 Functional check
Check the free and easy movement of
moving parts. The crane D-ring (1) must
move easily and without tilting (Over-
view Page 1) in the limit stop (2).
Implementation of anything beyond the
usual scope of inspection is subject to
the discretion of the competent person
and can extend to additional checks.
Checks and Inspections
4.4 Measures
If any defects are determined during the
safety inspection, they must be elimi-
nated according to the instructions pro-
vided by the inspector. A new inspection
is subsequently carried out.
4.5 Inspection before working opera-
tions begin
Check Platform Connection CB 160 for
any defects.
Ensure that the Platform Connection
CB 160 is securely in position.
Ensure lifting gear is correctly attached.
Initially raise and lower the working
scaffold or working platform only a
short distance from the ground, then
set down and eliminate any tension.
Check that the Platform Connection
CB160 is securely in position.