Operating Instructions MSA 2 MULTI Fusion process
15
When the operator confirms his intent of starting the fusion
process, pressing the START/OK ( I ) button, the unit will start to
weld.
In case of inconsistency between measured versus read
parameters the machine shows a message screen, with the
error message like the following one (fitting resistance too high
in respect to the nominal value).
E-10
12/06/12 15:50 25°C
2.7 Preparation
As soon as the operator confirms with the START/OK button,
before starting the fusion process, the MSA 2 MULTI shows a
reminder to the operator to be sure that pipes have been
scraped, cleaned, aligned following the instructions of the fitting
manufacturers.