Conguration setup
N.B.: The columns must always have an even number (minimum 4 and maximum 8)
A) New conguration
Only possible if the trolleys are all on the descent limit switches.
As rst operation, to determine the MASTER column and the subsequent SLAVE columns.
1) When starting the switchboard, the following shall appear on the display:
> > L A S T C o n f i g < <
N E W C o n f i g
move down with the blue Key , to
L A S T C o n f i g
> > N E W C o n f i g < <
conrm with the black “ENTER” key
The following is displayed:
> > C o l M A S T E R < <
C o l S L A V E
determine the MASTER column by pressing the black “ENTER” key
> > CANBUS CONN 2 < <
W a i t S l a v e s
Now the display shows “Wait SLAVE”, which means that the system is waiting for you
to select/congure the SLAVE columns.
2) Shift to another column, when starting the switchboard the display shall show the following:
> > L A S T C o n f i g < <
N E W C o n f i g
move down with the blue key , to
L A S T C o n f i g
> > N E W C o n f i g < <
conrm with the black “ENTER” key
the following is displayed:
> > C o l M A S T E R < <
C o l S L A V E
move down with the blue button , to
C o l M A S T E R
> > C o l S L A V E < <
conrm the SLAVE column by pressing the “ENTER” black key
Now the SLAVE column receives from the MASTER column the conguration message and the display shows:
> > C h a n n e l 1 ?< <
C o l u m n 2
The operator should conrm the data pressing the black key “ENTER” ; the following will be displayed:
> > I D 2 C H 1 < <
S e l e c t e d
conrm the correct conguration of the SLAVE 2 column
N.B.: The operator must repeat the operations at point 2 for all columns of the power lift.