Initial Calibration: Create Profile Setup Wizard 15
INITIAL CALIBRATION
BOOM CAPACITY
34.When boom recirculation capabilities are installed on the spray boom, enter the volume contained in the spray
boom sections in the Boom Capacity field.
NOTE: By default, the Boom Capacity is set to 0.5 L [0.13 gal.] per meter of boom. For example, a 40 m boom
has a boom capacity around 20 L of water.
FIGURE 15. Boom Capacity
35.Touch the Next Page button to complete the Profile Setup Wizard.

Other manuals for Raven RCM

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Raven RCM and is the answer not in the manual?

Raven RCM Specifications

General IconGeneral
BrandRaven
ModelRCM
CategoryControl Unit
LanguageEnglish

Related product manuals