Rinnai 16 Commercial Manifold Pack OIM
Starting instructions
These are specic to the Manifold Pack and installation conguration:
MANIFOLD PACK WITH NO RETICULATION SYSTEM
•
Turn on power to each heater via the Socket Outlets
•
Open one or more outlets to generate water ow through the heaters. The outlet temperature should appear
in the maintenance monitor window on each heater. This is factory preset at 75°C but can be adjusted if
required, refer to relevant temperature settings for heaters. This indicates the units are operational.
•
Not all heaters may will re up as this is ow rate dependent. To verify all heaters are operational either open
more outlets or, if this is not practical, close the cold water valve underneath the currently operating heaters
to restrict the ow. Other heaters should then re up.
•
Clean all lters on completion
MANIFOLD PACK WITH RETICULATION SYSTEM
•
Turn on power to each heater via the Socket Outlets
•
Turn on the Ring Main pump to generate water ow through the heaters. The outlet temperature should
appear in the maintenance monitor window on each heater. This is factory preset at 75°C but can be adjusted
if required, refer to relevant temperature settings for heaters. This indicates the units are operational.
•
Not all heaters may re up as its ow rate dependent. To verify all heaters are operational either open some
outlets or, if this is not practical, close the cold water valve underneath the currently operating heaters to
restrict the ow. Other heaters should then re up.
•
Clean all lters on completion
INSTALLATION INSTRUCTIONS