BA.GB.12-27409-05-07-FTA-jr
9.4 Inspection and Maintenance
Before substantial inspection and repair works are started the Ruthmann-
Steiger must be cleaned. All defects found during the inspection have to be
eliminated immediately.
9.4.1 Inspection List / Maintenance List
Explanations concerning the intervals:
d = daily or per working shift
300 h = after 300 operating hours
600 h = after 600 operating hours
a = annually
= Inspection work
W = Maintenance work
S = Test by an expert
Inspection List / Maintenance List
Check for function and cleanness
visually for damage (fissures,
deformations, corrosion)
Check painting (scratches, crack-
offs)
Visual and function test of safety
devices
Regular inspection acc. to
BGR 500 - 2.10
Check inscription for complete-
ness and legibility