Time-of-use Mode: Battery charging period and discharging period can be set , during
charging period, battery can only be charged, while in discharging period, battery can only
be discharged, the rest of the period, battery will behave as Self-use mode.
6.6 Export Limit Setting
6.6.1 APP setting
There are two methods to control the export limit, the two methods are alternative to each other.
Method 1: Export limitation setting is to control the export electricity to the grid.
Method 2: Generation limit is to control the electricity generated by the inverter.
6.7 Self-test (For Italy)
Italian Standard CEI0-21 requires a self-test function for all inverter that connected to utility
grid. During the self-testing time, inverter will check the reaction time for over frequency,
under frequency, overvoltage and undervoltage. This self-test is to ensure the inverter is able
to disconnect from grid when required. If the self-test fails, the inverter will not able to feed
into the grid.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the SAJ HS2 Series and is the answer not in the manual?

SAJ HS2 Series Specifications

General IconGeneral
BrandSAJ
ModelHS2 Series
CategoryStorage
LanguageEnglish

Related product manuals