R6 Series Solar Inverter
49
6.4.1 APP Setting
There are two methods to control the export limit, the two methods are alternative to each other.
Method 1: Export limitation setting is to control the export electricity to the grid.
Method 2: Generation limit is to control the electricity generated by the inverter.
6.5 Self-test (For Italy)
talian Standard CEI0-21 requires a self-test function for all inverter that connected to utility grid. During the
self-testing time, inverter will check the reaction time for over frequency, under frequency, overvoltage and
undervoltage. This self-test is to ensure the inverter is able to disconnect from grid when required. If the
self-test fails, the inverter will not able to feed into the grid.
The steps of running Self-test are as followed:
Step 1: Connect a communication module (Wi-Fi/ 4G/ Ethernet) with
inverter (connection procedure can refer to eSolar Module Quick
Installation Manual)
Step 2: Select Italy for Country and choose your corresponding Grid
Code from Initial Setting.
Step 3: Start Self-test
You can choose self-test item required. Individual self-test time is
approx. 5 minutes. All self-test time is approx. 40 minutes. After the
self-test is completed, you can save the test report. If self-test is failed, please contact with SAJ or your
inverter supplier.