Details of installation
1. First measure the under surface of the structure as a horizontal plane and the side of
the structure as a vertical plane by spirit level as shown as below
2. First cabinet is placed in the middle of the bottom row with the stud rods in the middle of
the corresponding slot as shown as below, do not fix the nuts tightly.
3. Place the cabinets beside one another from the middle of the row to the sides as shown
as below, do not fix the nuts tightly
4. Finish the first row by same way as shown as below.