4.2 Flue pipes used for STS exhaust flue kit
When the flue duct (including extension) passes through a combustible wall or ceiling with combustible materials,
it should be insulated with 25mm or thicker insulation and then set apart from the wall or materials by 50mm or
more. When it passes through the ceiling, include an opening for inspection of the flue.
If the air supply duct is separated from the flue duct, the total length of the flue duct should be 3.0 M or less and
with 2 or less elbows.
The connection of the air supply hose must be sealed by the wire clamp to prevent any air loss. In the connection
of the flue duct and the flue elbow, In O-ring must be inserted to prevent leakage.
Do not use any aluminum duct as an extension. Use extension duct sets or elbows available through your
kyungdong distributor.
The flue duct which carries combustion waste gas should be firmly secured by the clamp so that it will not loosen
due to vibration. The parts where the band clamp is not used should be sealed with aluminum tape.
In the event the exhaust pipe passes through a combustible wall or an combustible ceiling, insulate it with
nonflammable materials of 25mm thick or more and locate 50mm or more away from any combustible materials.
In addition, install a check port if flue passes through the ceiling.
Tie up a joint of the air intake hose with the wire clamp so as not produce a loss of an intake air, insert an O-ring in a
joint of the exhaust pipe and exhaust elbow so that the exhaust gas won’t leak.
Fix the exhaust pipe with the band clamp and screws so as not to pull due to shock. Make sure to wrap any pipe joint
not using a band clamp with aluminum tape.
Fig. Schematic of Standard Flue kit Installation
Ceiling
Seal opening to ensure that burne
waste gas does not enter the room.
In the event the intake hose is to
o
long, cut the shortest length as
possible and connect it.
Nonflammable
wall
150 or more
250or
more
500 or
more
Install the horizontal part of flue downwards(120mm)
so that the condensed water from the flue or rain doesn’t enter
into the boiler.
Install the flue in a place where there are no any obstacle
s
within 1.5M away from the flue.
Install the flue ensuring no that it cannot be blocked by sno
w
falling from the roof eaves.
Install the flue in a place in a location opening exist within 500 m
m
from the flue so that exhaust gas can’t re circulator in to the building.
Install the flue at least 600mm above the ground.
Unit : mm