2. Installation and preparation
2-1 Transportation of the machine
When lifting the machine with a crane at the factory site, insert two round bars of about
1-3/8 inch in diameter and use a wire suspension rope of sufficient strength to bear a load of
6,600 lbs. Pieces of wood and cloth should be inserted at the points where the rope touches
the machine to absorb impacts which may later influence the accuracy of the machine.
Fig. 2