Side-Power SR 100/185 T - Installation Checklist and Pre-Delivery Tests; Pre-Installation System Checks; Post-Installation and Delivery Checks

Default Icon
24 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
18
SR80/185T - SR100/185T 1.0.0 - 2009
Signatur: ............................................... Dato: ................................
Anbefalt før leverings test for installør / verft som ikke bruker andre
kvalitetskontroll systemer!
Thrustertype: ................................................ Volt: .............................
Serienummer: .....................................................................................
Leveringsdato: ....................................................................................
.RUUHNWNM¡UHUHWWQLQJSHUNRQWUROOSDQHO
6SHQQLQJPnOWSnWKUXVWHUXQGHUNM¡ULQJ
Strømkabler: .......................................................................................
6NRWWHWKYRUWKUXVWHUHQHUPRQWHUWHULVROHUWIUDNM¡OYDQQRJKDULQJHQ
nSHQEDUULVLNRIRUOHNNDVMH
Kommentar fra installør:
F Propeller is fastened correctly to the shaft.
F Propeller turns freely in tunnel.
F The zinc-anode holding screw is tightened well with thread glue.
F Anti-fouling have been applied to the gearhouse and propeller but
NOT on the zincanode or the gearhouse lid where the propeller is
fastened.
F 7KHEUXVKVSULQJVDUH¿WWHGFRUUHFWO\RQWKHEUXVKHVLQWKHHOHFWUR
motor (check through the grid around the top end of the motor).
F Correct drive direction as per controlpanel.
F All electrical connections are clean, dry and tight, and the correct
cable, fuse and main switch sizes have been used.
F With a ohm meter check that there is no electrical connection
between electromotor body and positive terminal on the motor and
between the electromotor body and the negative (A1) terminal on
the motor.
F The bolts holding the gearhouse and motorbracket together are
tightened correctly.
F The bolts holding the electromotor to its bracket are tightened
correctly.
Checklist
GB
The thruster has been installed as per the instructions in this manual and
all points in checklist above have been controlled.
Signed: ................................................ Date:...............................
Extra pre-delivery tests by installer/yard who does not use other
quality control systems !
Thruster type: .................................................. Voltage: ....................
Serial number: ................................. Date of delivery: .......................
Correct drive direction as per control panel: .....................................
Voltage at thruster when running: ......................................................
Battery cable size used: .....................................................................
7KHFRPSDUWPHQWZKHUHWKHWKUXVWHULV¿WWHGLVLVRODWHGIURPJHQHUDOELOJH
ZDWHUDQGKDVQRREYLRXVRUVXVSHFWHGULVNVIRUÀRRGLQJ
Other comments by installer:
Sjekkliste
N
F Propellen er festet til akselen på korrekt vis.
F Propellen roterer fritt i tunnel.
F )HVWHVNUXHQWLOVLQNDQRGHQHUIHVWHWPHGJMHQJHOLP
F Bunnstoff er påført girhus og propell, men ikke på sinkanode,
tetninger eller propellaksel.
F %¡UVWHIMUHQHHUULNWLJSODVVHUWPRWE¡UVWHQH'HWWHVMHNNHVYHGnVH
JMHQQRPJLWWHUHWSnVLGHQDYPRWRUHQ
F .RQWUROOSDQHOJLUNRUUHNWNM¡UHUHWQLQJSnWKUXVWHUHQ
F Alle elektriske koblinger er rene, tørre og tette. Korrekte kabler,
sikringer og hovedstrømsbryter er brukt.
F Boltene som festet braket til girhus er festet korrekt.
F Boltene som festet motor til braket er festet korrekt.
Thrusteren er installert i henhold til instuksene gitt i denne manualen, og
alle punkter i sjekklisten er kontrolert.