Appendix D: Acceptance Test Procedures
78 Siemens Energy & Automation, Inc.
Figure D.1 Terminal Connections for Test Procedures
I
A
V
A
V
B
V
C
I
N
I
B
I
C
Trip 1
CT 1-1
CT 2-1
CT 3-1
CT N-1
CT 1-2
CT 2-2
CT 3-2
CT N-2
VT 1+
VT 2+
VT 3+
VT 1-
VT 2-
VT 3-
Trip 2
Trip 3
Trip Common
Binary
Input 3
Binary
Input 1
Binary
Output 1
Binary
Output 2
Binary
Input 4
Binary
Input 2
I
TS
V
TS
50/51
50/
51N
2
1
29
11
30
31
33
32
34
21
41
43
45
3
4
5
6
7
8
9
10
42
44
46
23
25
27
22
24
26
28
Test Equipment
ISGS Relay
ISGS Relay
D
isv3o_1.bk : isv3otst.frm Page 78 Wednesday, August 7, 1996 10:51 AM