Do you have a question about the Siemens SBA 2000 and is the answer not in the manual?
Brand | Siemens |
---|---|
Model | SBA 2000 |
Category | Circuit breakers |
Language | English |
Step-by-step instructions for preparing and installing the stationary drawout element.
Instructions for uncrating, lifting, and installing the moveable drawout element.
Instructions for preparing and securing fixed-mounted breakers in the switchboard.
CAUTION about breaker state, and steps to remove the front cover for trip unit installation.
CAUTION, checking plug label, inserting/removing rating plug, and replacing cover.
Details controls and indicators on the front panel for breaker operation.
Step-by-step guide for manually charging the stored energy mechanism.
Instructions for locally closing the breaker, including necessary conditions and warnings.
Instructions for locally opening the breaker.
Defines the four positions (Connected, Test, Unlocked, Withdrawn) of the drawout element.
Steps to move the drawout element between the fully withdrawn and unlocked positions.
Step-by-step guide to rack the element from unlocked to test position using controls.
Steps to rack the element from test to connected position using controls.
Steps to rack the element from connected to test position using controls.
Steps to rack the element from test to unlocked position using controls.
Explains System Check Indicator, Trip Status, and Integral Test Modes for trip unit monitoring.
Illustrates time current curve adjustments for trip units, including pickup and delay settings.
Explains adjustments for continuous current pickup and long time delay settings on trip units.
Details settings for short time pickup levels and time delay parameters for fault protection.
Explains how to set the instantaneous trip current level for immediate fault response.
Covers ground fault pickup levels and delay settings for selective tripping.
Explains the function, components, and installation of the electric motor operator.
Describes the UVR, its operation, voltage ratings, and installation process.
Explains the shunt trip's capability for remote opening and its installation.
Details the Ground Fault Monitor (GFM) and its settings for ground fault current monitoring.
Details ground fault pickup levels (LO, HI, MED) and delay bands for the GFM.
Designed for residual/source ground fault protection and is mounted on a bus bar.
Procedures for using the TS-31 test kit to test breaker functions and settings.