SITRANS P, DS III series (7MF4.33.. 7MF4.34.. 7MF4.35..)
28 A5E03434631-02, 12/2012
Transmitter above the differential pressure
transducer
Transmitter below the
differential pressure transducer
Condition
All shut-off valves are closed.
Procedure
To commission the transmitter for gases, proceed as follows:
1. Open both the shut-off valves
⑥ at the pressure tapping point.
2. Open the stabilizing valve
②.
3. Open the differential pressure valve (
③ or ④).
4. Check and if required correct the zero point when the start of scale value is 0 mbar (4 mA).
5. Close the stabilizing valve
②.
6. Open the other differential pressure valve (
③ or ④).
5.4.3 Commissioning for liquids
Usual arrangement Special arrangement
①
Pressure transmitter
⑦
Drain valves
②
Equalizer valve
⑧
Gas collector vessels (optional)
③, ④
Differential pressure valves
⑨
Differential pressure transducer
⑤
Differential pressure lines
⑩
Vent valves
⑥
Shut-off valves
Transmitter below the differential pressure
transducer
Transmitter above the
differential pressure transducer