Less than 0.002A within 20minsat 340nm
Repetition of absorbency
Coefficient variance(CV) ≤1.0%
Cross Contamination Rate:
When reaction liquid volume is 1ml, the cross contamination rate should be less than
1% by flow cell test; no cross contamination by using separated cuvette inspection.
2. Installation
In order to ensure the equipment works normally, it must be installed and debugged by the
engineers who are authorized by Sinnowa or Sinnowa authorized organization. For any reasons
to reinstall the analyzer, only the authorized engineer can do the works.
Attention: No authorized installation may make wrong or damage the equipment, the
problem or damage is not in term of free warranty.
2.1 Installation Requirement
2.1.1 Space Requirement
1.Keep the analyzer not less than 100mm distance from wall and other objects for each
side(left, right and back)
2.Ensure enough space for the equipment to place barrel of distilled water and waste
container
2.1.2 Environmental Requirement
1.Working Temperature: 15℃ ~ 32℃
2.Working Humidity: 30% ~ 70%;
3.Working atmospheric pressure: 860hPa ~ 1060hPa;
4.Power supply: 220V~ ±10%,50Hz±1 Hz;
5.Fuse: F2AL250V,Ф5x20mm;Fuse:
6.Input Power : 150VA;
7.A good grounding socket within 1meter of the equipment
8.The environment should be in quiet and clean room, and keep away from dust, noise and
power interference.
9. The equipment should keep away from the equipments like Centrifuge, CT, X-ray
machine and radio interference, etc.
10.Avoid direct sunlight and ultraviolet rays and keep away from hot and cool source,
outlet of air condition.
Attention:
The power supply socket should be within 1meter from the analyzer in order to pull out the
plug timely when accident happens
Check if network voltage is the same to the equipment voltage and confirm the power
supply is in stable conditions (the voltage change is within 10%)