This manual describes the mounting, installation and commissioning of a DOL 278T controlled emergency
opening system and is aimed primarily at the technicians and electricians who will be mounting, installing and
testing the emergency opening system.
The following checklist indicates the main points of the work flow regarding set up of the emergency opening
system.
Mounting
1. DOL 278T.
2. Temperature sensors.
Installation
1. Battery.
2. Test supply separator.
3. Setting the supply voltage.
4. Connect cables according to the wiring diagram.
5. Connection to the house controller.
6. Connecting supply voltage.
7. Setting of house controller.
Testing
1. DOL 278T.
2. Battery.
3. Temperature sensors.
Start-up
1. Setting