SMA Solar Technology AG 4 Service
Installation Guide SHP75-10-STP60-10-IA-xx-18 37
System-Related Events
Table 4.3 System-related events
ID Status
message
Description Measures DNO SMA
Service
Line
PV
2000 Communication assembly is
booting.
----
2010,
2011
The software update of the
main CPU has started / has
finished.
----
2012 -
2018
The software update failed. Restart the software update. If an
error occurs during the update,
contact Service.
-x-
2030 Transmission of the grid code
to the main computer failed.
If this event occurs frequently,
contact Service.
-x-
2050 Ethernet connection is active No measure necessary. This error is
used, for example, to identify bad
Ethernet cables.
---
2051 Ethernet connection is
disconnected
No measure necessary. This error is
used, for example, to identify bad
Ethernet cables.
---
2052,
2053
Transmission of the Grid Code
from the SMA Inverter
Manager to the inverter has
started/ended.
----
2054 Transmission of the Grid Code
from the SMA Inverter
Manager to the inverter has
failed.
If this event occurs frequently,
contact Service.
---
2055 Fallback
activated
The inverter switched to the
fallback mode after the
communication with the SMA
Inverter Manager was
interrupted.
---
2056 Fallback
completed
The inverter has switched back
to normal operation after
having been in the fallback
mode due to a communication
disturbance with the SMA
Inverter Manager.
---